Hotel HSM Don Juan

Project scope

Electrical, mechanical and hydraulic works across all seven floors of the hotel, including technical rooms, reception, kitchen, guest rooms, corridors and common areas, with the goal of upgrading and commissioning the building.

Year

2025-2026

Location

Calviá, Illes Balears
Hotel HSM Don Juan
Hotel HSM Don Juan

The intervention at HSM Don Juan Hotel in Calvià focused on the comprehensive reopening and expansion of the building through the upgrade of its MEP services.

The project was carried out across all seven floors and included a wide range of electrical, mechanical and hydraulic works tailored to the operational requirements of a large-scale hospitality facility.

On the electrical side, the works included floor-by-floor construction boards, main power supply, lighting and socket wiring, as well as the installation of LED panels, weatherproof outlets and dedicated connections for the goods lift and service areas. In parallel, the mechanical scope covered piping works, stormwater networks, provisional and permanent connections, and routing adjustments in different parts of the building.

Hotel HSM Don Juan
Hotel HSM Don Juan

On the electrical side, the works included floor-by-floor construction boards, main power supply, lighting and socket wiring, as well as the installation of LED panels, weatherproof outlets and dedicated connections for the goods lift and service areas. In parallel, the mechanical scope covered piping works, stormwater networks, provisional and permanent connections, and routing adjustments in different parts of the building.

Hotel HSM Don Juan

The project also covered key areas such as reception, kitchen, guest rooms, corridors, technical spaces and common areas, with a planning approach designed to restore full hotel operability within the scheduled timeframe.

  • Floors 7
  • Budget 23 millions
  • Exec Time 6 M

Photos courtesy of

  • HSM Don Juan